Families, Children & Learning – Capital Budget Summary

 

Forecast Variance Month 2

Unit

Reported Budget Month 2

Reported at Other Committees

New Schemes

Variations, Slippages & Reprofiles

Reported Budget Month 5

Forecast Outturn Month 5

Forecast Variance Month 5

Forecast Variance Month 5

£'000

£'000

£'000

£'000

£'000

£'000

£'000

£'000

%

0

Director of Families, Children & Learning

0

0

0

0

0

0

0

0.0%

0

Health, SEN & Disability Services

0

0

0

0

0

0

0

0.0%

0

Education & Skills

16,847

0

0

0

16,847

16,847

0

0.0%

0

Schools

2,662

0

0

0

2,662

2,662

0

0.0%

(35)

Children's Safeguarding & Care

35

0

0

0

35

0

(35)

-100.0%

0

Quality Assurance & Performance

0

0

0

0

0

0

0

0.0%

(35)

Total Families, Children & Learning

19,544

0

0

0

19,544

19,509

(35)

-0.2%

 

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

Amount
£'000

Project

Description

Children's Safeguarding & Care

Variance

(35)

Contact Supervision Centres

Variance of less than £0.100m.

 

 

 

 

 

 

 

 

 

 

 

 

Health & Adult Social Care – Capital Budget Summary

 

Forecast Variance Month 2

Unit

Reported Budget Month 2

Reported at Other Committees

New Schemes

Variations, Slippages & Reprofiles

Reported Budget Month 5

Forecast Outturn Month 5

Forecast Variance Month 5

Forecast Variance Month 5

£'000

£'000

£'000

£'000

£'000

£'000

£'000

£'000

%

84

Adult Social Care

2,300

0

0

0

2,300

2,426

126

5.5%

0

Integrated Commissioning

0

0

0

0

0

0

0

0.0%

0

S75 Sussex Partnership Foundation Trust (SPFT)

0

0

0

0

0

0

0

0.0%

0

Public Health

0

0

0

0

0

0

0

0.0%

84

Total Health & Adult Social Care

2,300

0

0

0

2,300

2,426

126

5.5%

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

Amount
£'000

Project

Description

Adult Social Care

Variance

30

Better Care Fund – Adaptions for the Disabled

Variance of less than £0.100m

Variance

95

Better Care Fund - Telecare

Variance of less than £0.100m

 Variance

1

 Knoll House Building Works

Variance of less than £0.100m

 

 

 

 

 

 

 

 

 

Economy, Environment & Culture (excluding Housing Revenue Account) – Capital Budget Summary

 

Forecast Variance Month 2

Unit

Reported Budget Month 2

Reported at Other Committees

New Schemes

Variations, Slippages & Reprofiles

Reported Budget Month 5

Forecast Outturn Month 5

Forecast Variance Month 5

Forecast Variance Month 5

£'000

£'000

£'000

£'000

£'000

£'000

£'000

£'000

%

0

Transport

36,368

75

0

(4,637)

31,806

31,806

0

0.0%

0

City Environmental Management

15,063

23

0

(200)

14,886

14,886

0

0.0%

0

City Development & Regeneration

8,825

0

0

0

8,825

8,825

0

0.0%

0

Culture, Tourism & Sport

18,118

70

0

514

18,702

18,702

0

0.0%

0

Property

11,865

175

1,496

(1,601)

11,935

11,935

0

0.0%

0

Total Economy, Environment & Culture

90,239

343

1,456

(5,924)

86,114

86,114

0

0.0%

 

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

Amount
£'000

Project

Description

Transport

Reported at Other Committee

75

Norton Road Rain Gardens

Reported at Other Committees - as part of the Carbon Neutral Fund.

Reprofile

(4,637)

Valley Gardens Phase 3 (LTP)

The scheme has been paused following a review of the project. The majority of the project expenditure will now likely be incurred next financial year. A reprofile of the budget is required to meet the current timetable.

City Environmental Management

Reported at Other Committee

10

Electrical Vehicle for Waterhall

Reported at Other Committees - as part of the Carbon Neutral Fund.

Reported at Other Committee

13

Rechargeable Medium Sized Machinery Parks

Reported at Other Committees - as part of the Carbon Neutral Fund.

Variation

(200)

Public Conveniences

A variation of £0.200m is requested to support the Kingsway to the Sea project in delivering new toilet facilities (see below).

Culture, Tourism & Sport

Reported at Other Committee

70

Levelling Up/Kingsway to the Sea

Less than £0.100m.

Variation

204

King Alfred Main Pool Reinforcement

Budgets to be amalgamated onto main project code as works being carried out as one project.

Variation

60

Prince Regent Capital Works

Variation of less than £0.100m.

Variation

250

Levelling Up/Kingsway to the Sea

Additional Levelling Up Fund grant has been awarded of £0.050m for to support resourcing capacity. A contribution of £0.200m from the City Clean Public Conveniences budget for the refurbishment of existing and development of new toilet facilities will also be added to the Kingsway to the Sea budget in 2023/24.

In addition, a further sum of £1.290m will be added to the 2024/25 met from Section 106 contributions. In June 2023 the Strategic Finance & City Regeneration Committee approved a total budget of £13.761m and a reduction in project scope to fit within this budget. Subsequent feedback from the community strongly requested the reintroduction of sand sports area and lighting for the park back into the project scope.

The reinstatement of these facilities and some support the wider project requirements could be enabled by the use of additional S106 funds, the majority of these funds being taken from future Section 106  receipts.

Property

Reported at Other Committee

100

Cemeteries Structural Works

Allocation of the 2023/24 Planned Maintenance Budget towards structural works for cemeteries. Originally reported to committee in March 2023.

Reported at Other Committee

50

Victoria Fountain Repairs

Less than £0.100m

Reported at Other Committee

25

Hollingdean Depot

Less than £0.100m

Variation

(773)

Carbon Reduction Measures to Operational Buildings

Allocated to the new capital scheme for provision of solar panels on corporate buildings (see Appendix 7).

Variation

(204)

King Alfred Cathodic Protection System Repairs

Budgets to be amalgamated onto main project code as works being carried out as one project.

Variation

(98)

Crowhurst Road PMB

Variation of less than £0.100m.

Variation

(60)

Planned Maintenance for Council Leisure Buildings

Variation of less than £0.100m.

Variation

(20)

External Improvement Works

Variation of less than £0.100m.

Variation

(3)

Provision of Drinking Water Fountains

Variation of less than £0.100m.

Variation

50

Victoria Fountain Repairs

Variation of less than £0.100m.

Variation

38

Barts Cladding & Window Replace Phase 1

Variation of less than £0.100m.

Variation

11

Mechanical Boiler Replacement - Mechanical

Variation of less than £0.100m.

Variation

10

Window Replacement Cottages Property Portfolio

Variation of less than £0.100m.

Variation

9

Fire Safety Improvements

Variation of less than £0.100m.

Reprofile

(210)

Imperial Arcade PMB

Roof works already reported for up to £0.060m of essential repairs to be undertaken in year. The balance of £0.210m to be reprofiled into 2024/25 for façade refurbishment.

Reprofile

(105)

Mile Oak Community Centre PMB

Essential repairs in line with spending restrictions estimated at £0.025m. The remaining budget of £0.105m to be provisionally reprofiled into 2024/25 for refurbishment.

Reprofile

(40)

Statutory DDA Access Works Fund

Reprofile of less than £0.100m.

Reprofile

(10)

Hollingdean Depot

Reprofile of less than £0.100m.

Slippage

(196)

Madeira Terrace Structure Repair & Resurface

Around £0.150m will be spend on prioritised H&S works in 2023-24, the balance of £0.196m is to be slipped into 2024-25 to fund the next prioritised temporary propping works.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Housing, Neighbourhoods & Communities (excluding Housing Revenue Account) – Capital Budget Summary

 

Forecast Variance Month 2

Unit

Reported Budget Month 2

Reported at Other Committees

New Schemes

Variations, Slippages & Reprofiles

Reported Budget Month 5

Forecast Outturn Month 5

Forecast Variance Month 5

Forecast Variance Month 5

£'000

£'000

£'000

£'000

£'000

£'000

£'000

£'000

%

0

Housing General Fund

4,633

0

0

4,633

4,633

0

0.0%

4,633

0

Libraries

250

0

0

250

250

0

0.0%

250

0

Communities, Equalities & Third Sector

0

0

0

0

0

0

0.0%

0

0

Safer Communities

0

0

0

0

0

0

0.0%

0

0

Total Housing, Neighbourhoods & Communities

4,883

0

0

4,883

4,883

0

0.0%

4,883

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

Amount
£’000

Project

Description

Housing, Neighbourhoods & Communities

 

 

 

There are no budget changes to report for TBM month 5.

 

 


Housing Revenue Account (HRA) – Capital Budget Summary

 

Forecast Variance Month 2

Unit

Reported Budget Month 2

Reported at Other Committees

New Schemes

Variations, Slippages & Reprofiles

Reported Budget Month 5

Forecast Outturn Month 5

Forecast Variance Month 5

Forecast Variance Month 5

£'000

£'000

£'000

£'000

£'000

£'000

£'000

£'000

%

78

City Development & Regeneration

20,736

11,250

0

(7,776)

24,210

24,313

103

0.4%

(2,597)

Housing Revenue Account

75,859

(11,250)

0

(18,651)

45,958

46,176

218

0.5%

(2,519)

Total Housing Revenue Account

96,595

0

0

(26,427)

70,168

70,489

321

0.5%

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

Amount
£'000

Project

Description

City Development & Regeneration

 

Reported at Other Committees

 

11,250

Kubic Apartments

Reported at July 2023 Strategic, Financial & City Regeneration committee meeting relating to the purchase of Kubic Apartments, Whitehawk Way.

Reprofile

(7,320)

Moulsecoomb Hub Housing

Procurement and delivery options are being reviewed alongside RIBA stage 4 technical design work, so start on site and the necessary appropriation has been delayed. A report outlining Options will be going to Housing & New Homes Committee in November.

Reprofile

(135)

Windlesham Close

A more detailed cashflow has been produced, and the overall project programme was extended by two months since the last update.

Reprofile

(170)

Frederick Street

There has been a delayed start on site, a meaningful start was achieved in April 2023, with construction phase commencing in August 2023. This was due to delays securing necessary Highways consents, site set up and welfare facilities and finalising temporary works design and party wall issues with adjoining property owners.

Reprofile

(151)

Rotherfield Crescent

There has been a delayed procurement programme, due to an unsuccessful first tender, the project was repackaged and retendered. The project is due to start on site in November 2023. The reprofile reflects the new cashflow profile.

Variance

152

Victoria Road

The final account for Victoria Road is due to be agreed in 2023/23 and is currently under negotiation between our QS and contractor. This variance is the latest estimate, the final account is due to be settled imminently.

 

Variance

(49)

Charles Kingston Gardens

Variance of less than £0.100m.

 

 

 

Housing Revenue Account

 

Reported at Other Committees

(6,045)

Home Purchase Scheme

Reported at July 2023 Strategic, Financial & City Regeneration committee meeting relating to the purchase of Kubic Apartments, Whitehawk Way.

Reported at Other Committees

(5,205)

Extended Home Purchase Scheme

Reported at July 2023 Strategic, Financial & City Regeneration committee meeting relating to the purchase of Kubic Apartments, Whitehawk Way.

Variation

800

Condensation & Damp Woks

There has been a significant increase in damp and condensation cases reported from when the budget was set for the current financial year.

Variation

500

New Housing Management IT System

Realignment of HRA ICT budgets to reflect the delivery routes.

Variation

420

Roofing

Project moved from Structural Repairs budget line to reflect works being carried out.

Variation

(420)

Structural Repairs

Project delivery moved to Planned Works - Roofing budget.

Variation

(800)

Home Efficiency & Renewables

Budget variation to reflect forecast spend against planned projects this financial year and transfer to the Condensation & Damp works budget line to reflect the additional spend increasing energy efficiency through cavity wall insulation and other works.

Variation

(250)

New Housing Asset Management System

Realignment of HRA ICT budgets to reflect the delivery routes.

Variation

(250)

New Housing Works Management System

Realignment of HRA ICT budgets to reflect the delivery routes.

Reprofile

(9,844)

Home Purchase Scheme

The housing market dictates the number of purchases that can be completed in a year. After reviewing the house under offer and due to complete a reprofile of budget is required to reflect the current estimate of new homes being acquired. The new budget is expected to be utilised during 2024/25.

Reprofile

(5,972)

Structural Repairs

Mobilising works contracts has led to changes to the planned start date for major projects. Procurement, resident engagement and leaseholder consultation continues to be undertaken during this stage. The spending profile will continue to be monitored and updated throughout the financial year.

Reprofile

(1,495)

Palace Place Redevelopment

The redevelopment hasn’t progressed at the pace expected it is currently showing an increased viability gap, a revised business case will be required which considers the  construction cost inflation which will have a downward pressure on the residual value of the site. Any new costs are expected to be utilised in 2024/25.

Reprofile

(668)

Housing First

The housing market dictates the number of purchases that can be completed in a year. After reviewing the house under offer and due to complete a reprofile of budget is required to reflect the current estimate of new homes being acquired. The new budget is expected to be utilised during 2024/25.

Reprofile

(482)

Sheltered Services System

Changes to some of the planned start dates against the lift replacement programme.

Reprofile

(190)

HRA Owned Playgrounds Refurbishment

Phase 2 of the refurbishment programme to be reprofiled to 2024/25.

Variance

600

External Decorations & Repairs

Additional spend arising from a need to carry out urgent works to timber cladded blocks that was not allowed for in the budget.

Variance

330

Minor Capital Works

There is a forecast overspend as a result of several large projects, which are significantly higher cost when compared to business as usual projects against this budget line.

Variance

290

Domestic Rewire

Additional costs expected due to new legislation for domestic installations and a potential increase in the volume of rewires arising from the new EICR testing programme.

Variance

(200)

HRA Adaptations

There is an underspend forecast, based on contractor capacity (high demand for builders).

Variance

(400)

Kitchens

There has been a significant underperformance by the planned works contractor for kitchen replacements which has resulted in an underspend. To address this performance issue, approval was given by Housing Committee (16th November 2022) to procure up to two further contractors for this work stream and an improved spend against this budget should be seen.

Variance

(402)

Various Schemes

Variances of £0.100m or less across the following schemes:

 

 

 

£0.050m – Empty Properties

 

 

 

£(0.100)m – Environmental Improvements

 

 

 

£(0.088)m – City Wide Loft Conversions

 

 

 

£(0.080)m – Door Entry Systems & CCTV

£(0.034)m – Communal Fire Alarms

 

 

 

£0.060m – Sheltered Services Systems

£(0.100)m – Water Tanks

£(0.040)m – Communal Boilers

£0.080m – Domestic Boiler & systems Installation

£(0.100)m – Main Entrance Doors

£(0.050)m – Senior Housing Improvements

 

 


Governance, People & Resources - Capital Budget Summary

 

Forecast Variance Month 2

Unit

Reported Budget Month 2

Reported at Other Committees

New Schemes

Variations, Slippages & Reprofiles

Reported Budget Month 5

Forecast Outturn Month 5

Forecast Variance Month 5

Forecast Variance Month 5

£'000

£'000

£'000

£'000

£'000

£'000

£'000

£'000

%

0

Chief Executive Monitoring Office

0

0

0

0

0

0

0

0.0%

0

Policy & Communications

0

0

0

0

0

0

0

0.0%

0

Legal & Democratic Services

0

0

0

0

0

0

0

0.0%

0

Life Events

0

0

0

0

0

0

0

0.0%

0

Customer Modernisation & Data

0

0

0

0

0

0

0

0.0%

0

Finance

242

0

0

0

242

242

0

0.0%

0

Procurement

0

0

0

0

0

0

0

0.0%

0

HR & Organisational Development

251

0

0

0

251

251

0

0.0%

0

IT&D

5,243

0

0

150

5,393

5,393

0

0.0%

0

Welfare Revenue & Business Support

0

0

0

0

0

0

0

0.0%

0

Housing Benefit Subsidy

0

0

0

0

0

0

0

0.0%

0

Contribution to Orbis

0

0

0

0

0

0

0

0.0%

0

Total Governance, People & Resources

5,736

0

0

150

5,886

5,886

0

0.0%

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

Amount
£'000

Project

Description

IT&D

 

 

 

Variation

150

Digital Organisation Programme

The council’s core business applications and services run in the Shared Orbis Datacentre comprising of separate Nutanix nodes that provide resilient and secure platforms for the council’s applications. The replacement of these nodes are required at a cost of £0.150m for this year plus a further £0.400m profiled for 2024/25. The funding was identified in the Digital Data and Technology investment business case earlier this year. Although initially identified as non-essential, this initial part of the investment should have been ear marked as essential and is an oversight of the original business case creation.

 

 

 